Site icon Your Gateway to Power Transmission & Distribution

ISTS schemes for 25.8 GW RE evacuation approved in 2025

Interstate transmission system (ISTS) schemes for evacuation of 25.8 GW of renewable energy were approved during the January-November period of 2025, a government release said.

These projects entail estimated investment of Rs.38,849 crore. The release, outlining the country’s achievements in the power sector during 2025, said that transmission network with capacity 335 GW would be needed to connect 280 GW of variable renewable energy to the ISTS network by 2030.

Of this, 48 GW has already been completed while another 172 GW is under construction. Schemes worth 18.5 GW are under bidding while the remaining 96.5 GW will be approved in due course.

 

Here are some more highlights of the annual review

Also read: ISTS-TBCB market in 9MFY26: 12 schemes, 7 winners, Adani Energy enjoys highest market share