NKT wins its largest order ever, to supply 525kV cables to Germany

NKT

NKT has been awarded its largest order ever — of over 1 billion Euros .Placed by TenneT and TransnetBW, the contracts comprise the supply and installation of a 525kV XLPE high-voltage DC (direct current) onshore cable system with a route length of approx. 750 km for the German SuedLink corridor.

The SuedLink corridor comprises two power cable systems, and NKT has been awarded the 2-GW cable link which will be the world’s largest and longest high-voltage DC underground interconnector. The SuedLink line starts in Northern Germany where it connects to power from offshore wind farms and to the Nordlink interconnector, which brings hydro power from Norway to Germany via a 525kV high-voltage DC offshore power cable system also provided by NKT. In May this year, NKT announced to also deliver the majority of the 525 kV XLPE power cable system for the SuedOstLink corridor in Eastern Germany.

According to NKT President and CEO Alexander Kara, “The order for the SuedLink corridor project underlines NKT’s position as a major partner in Germany’s transition towards increased use of renewable energy and in connecting the national grids. Our power cable systems will ensure that wind and hydro power can be transported all the way from the North Sea and Norway via the NordLink and SuedLink interconnectors to Southern Germany. As a market leading provider of high-voltage DC technology we are positioned to be part of future projects supporting the green transformation of societies.”

The power cables and accessories to be delivered for SuedLink comprises two lots which constitutes one out of two full power cable systems. Furthermore, the order comprises a specially engineered solution for the power cable to cross the Elbe river and a salt mine.

The NKT contract value of over 1 billion Euros in market prices, corresponds to over 875 million Euros in standard metal prices. NKT expects to start production early 2022 on its plants in Cologne, Germany and in Karlskrona, Sweden with expected project completion in 2026.

NKT has gradually increased its high-voltage order backlog since end-2018 to an all-time high of around 2.7 billion Euros. In addition, the company sees positive market outlook with growing project complexity and magnitude, and therefore intends to invest around 150 millon Euros during 2020-2022 to strengthen its high-voltage manufacturing facilities.

SuedLink is one of three long-distance high-voltage DC power transmission lines in Germany to transport renewable energy from the Northern parts of the country to the South, and it links the federal states of Schleswig-Holstein and Baden-Württemberg. In total, the three transmission lines will cover a significant proportion of the country’s power supply and are key to realize ‘Energiewende’, Germany’s long-term strategy for switching to renewable energies by 2050.

Featured photograph, sourced from www.nkt.com, shows production of high-voltage cables at one of NKT’s manufacturing plants.