Site icon Your Gateway to Power Transmission & Distribution

Patel Engineering Declared Lowest Bidder (L1) for ₹1,441.04 Crore Gongri Hydropower Project in Arunachal Pradesh

Patel Engineering Declared Lowest Bidder (L1) for ₹1,441.04 Crore Gongri Hydropower Project in Arunachal Pradesh

Image Source: Kameng hydroelectric dam Patel Eng

Patel Engineering Limited has been declared the lowest bidder (L1) by its wholly owned subsidiary, Dirang Energy Private Limited (DEPL), to construct the 144 MW (2×72 MW) Gongri Hydro Electric Project in Arunachal Pradesh’s West Kameng district at a contract value of ₹1,441.04 crore inclusive of GST.

Disclosed in a regulatory filing, the civil and electromechanical mandate carries a 48-month execution timeline from the date of award. Because DEPL serves as the special purpose vehicle developing the project on a Build-Own-Operate-Transfer (BOOT) basis under a 40-year lease period, the award qualifies as a related-party transaction executed on an arm’s-length basis.

Situated on the Gongri River-a tributary of the Bichom River in the Kameng basin near Dirang town-the run-of-the-river installation is engineered to generate 623.19 million units (MU) of electricity annually at 90% dependable water flow and 95% plant availability.

Under the scope of work, the Mumbai-headquartered infrastructure contractor will build a diversion barrage fitted with four radial gates, intake structures, and two desilting chambers. Water will be routed through a 7.1-km-long, 5.8-metre-diameter head race tunnel connected to a 13-metre-diameter surge shaft and a 647.26-metre pressure shaft feeding a surface powerhouse. The package also encompasses a tail race channel, an evacuation switchyard, and full hydro-mechanical and electro-mechanical equipment installation.

Commenting on the project milestone, Kavita Shirvairkar, Managing Director, Patel Engineering, said,”Executing the Gongri Hydro Electric Project allows us to apply our core engineering strengths directly to a strategic group asset. The 144 MW project will add clean, renewable power and support the development of Arunachal Pradesh. We are committed to delivering it safely, on time and to the highest standards.”

Established in 1949, Patel Engineering has delivered over 85 dams, 40 hydroelectric projects, and more than 300 km of tunnels across domestic and international markets.

Also read: Patel Engineering signs MoU for Gongri hydropower project revival