First unit of NTPC’s Barh (Stage-1) project starts trial operations

  NTPC, in a stock exchange filing, said that the first unit of its 3x660-mw Barh super thermal power project (Stage-1) has completed trial operations. The filing said that “based on achievement of approved norms and due approvals, Unit-1 of Read more

NTPC Barh 02 | T&D India

NTPC’s Barh Stage-1 project: CERC extends timeline for infirm power injection

  Central Electricity Regulatory Commission (CERC) has allowed interchange of power, including drawl of start-up power and injection of infirm power into the grid up to March 24, 2022, with respect to NTPC’s Barh thermal power project. The relaxation relates Read more

Barhh-NTPC-1 | T&D India

One more unit of Barh power plant synchronized to grid