INSULOGIX
Linxon SS | T&D India

Substation capacity addition falters at 765kV level

    Substation capacity addition during the first eight months (April to November) of FY24 fell substantially short of the target, especially considering the 765kV voltage class. According to latest statistics released by the Central Electricity Authority (CEA), Read more

Adani

Private sector meets FY24 target for 765kV line addition

    Private sector entities have met the FY24 target for addition of 765kV transmission lines, within just seven months. According to latest statistics released by Central Electricity Authority (CEA), the private sector was expected to add 1,659 ckm of 765kV Read more

Sterlite OPGW | T&D India

Transmission line addition meets just 52 per cent of target

  The quantum of transmission line addition during the first seven months (April to October) of FY23 has met just 52 per cent of the target set for the period. According to latest statistics released by Central Electricity Authority (CEA), Read more

NRSS-29 delivers Sterlite Power | T&D India

TBCB Report Card for H1 FY23: 4 awarded, 1 completed

  A special study by T&D India, based on official statistics, suggests that during the first half (April to September) of FY23, four new TBCB-based interstate transmission projects were awarded while one was completed. Awarded The study indicates that out of Read more

ER NER TBCB | T&D India

CEA revises transmission capacity targets for FY23

  Central Electricity Authority (CEA), under the Union power ministry, has announced a revision of targets for power transmission capacity addition for FY23. The targets for capacity addition in FY23 have been downwardly revised for both transmission lines and substations. In Read more

GIS Substation Bhuj | T&D India

FY23 to witness 27,000 MVA of 765kV substation addition

Ongoing fiscal year FY23 is likely to witness the addition of 27,000 MVA transformation capacity through 765kV substations, according to latest statistics released by Central Electricity Authority (CEA). Of the total planned addition, Power Grid Corporation of India Ltd Read more

IndiGrid New | T&D India

Transmission line addition target 10 per cent higher in FY23

The planned addition of transmission lines in the ongoing fiscal year FY23 has been set at a little over 21,000 ckm, which is nearly 10 per cent higher than the comparable level for FY22. The latest report of Central Read more

Substation General | T&D India

Substation capacity addition target up 17 per cent in FY23

  The targeted substation capacity addition for ongoing FY23 is up 17 per cent compared with that for FY22. According to the latest report released by Central Electricity Authority (CEA), the overall target for substation (transformation) capacity addition for FY23 Read more