India’s transmission line addition during the first five months (April to August) of FY26 met over 90 per cent of the target set for the period. According to latest statistics released by Central Electricity Authority (CEA), Read more
There has been significant downward revision in the targets for transmission line and substation capacity addition during FY26. Central Electricity Authority (CEA) has revised the transmission line addition target for FY26 by 37 per cent to Read more
The quantum of transmission line addition in the first quarter (Q1: April to June) of current year FY26 was less than 20 per cent of the planned addition. According to latest statistics released by Central Electricity Authority ( Read more
Ongoing fiscal year FY26 appears to have got off to a good start as far as substation capacity addition goes. Latest official statistics indicate that during the first two months (April and May) of FY26, total substation (transformation) capacity Read more
Significant transformation capacity addition was seen in April 2025, the opening month of the ongoing fiscal year FY26 with Power Grid Corporation of India Ltd (PGCIL) and Adani Energy Solutions Ltd (AESL) making important contributions. According Read more