Ladakh RE evacuation scheme: EHVAC found feasible, NCT’s approval awaited

It is now confirmed that the mega Ladakh renewable energy (RE) evacuation scheme will be implemented using EHVAC technology, instead of the earlier planned combination of HVDC and EHVAC. However, the final approval by National Committee on Transmission Read more

Tendering for Ladakh HVDC project delayed further

A further delay of around three months is likely in awarding contracts for the mega Ladakh HVDC project that Power Grid Corporation of India Ltd (PGCIL) has been mandated to develop under the regulated tariff Read more

Hitachi ABB HVDC | T&D India

PGCIL to place orders for Ladakh HVDC scheme in Q2FY26

Power Grid Corporation of India Ltd (PGCIL) now expects to finalize contracts for the Ladakh HVDC scheme during the second quarter (July to September) of the current fiscal year. At a recent investor conference, R.K. Tyagi, CMD, PGCIL, explained Read more

Contracts for Ladakh HVDC project to be awarded in Q1FY26

Power Grid Corporation of India Ltd (PGCIL) expects to awards contracts for its mega HVDC scheme in Ladakh in the first quarter (Q1: April to June) of FY26. PGCIL is developing the project under the Read more

Ladakh connectivity scheme | T&D India

Tendering for Ladakh HVDC project targeted by January 2025

    Power Grid Corporation of India Ltd (PGCIL) expects tendering activity for the mega Ladakh HVDC project to begin by January next year. Addressing an investor conference recently, R.K. Tyagi, CMD, PGCIL said that Read more

Champa Kurukshetra HVDC | T&D India

PGCIL begins FEED studies on Ladakh HVDC project

  Power Grid Corporation of India Ltd (PGCIL) has initiated FEED studies for the upcoming mega Ladakh HVDC project. Addressing a recent investor conference, G. Ravishankar, Director (Finance) & CFO, PGCIL, said that front-end engineering design (FEED) studies for the Read more