substation capacity

Major substation build-up seen in April 2025, AESL leads private sector addition

Significant transformation capacity addition was seen in April 2025, the opening month of the ongoing fiscal year FY26 with Power Grid Corporation of India Ltd (PGCIL) and Adani Energy Solutions Ltd (AESL) making important contributions. According Read more

MPPTCL Narmadapuram | T&D India

Substation capacity addition up 22 per cent in FY25

India added an impressive 86,433 MVA of transformation (substation) capacity in FY25 – a quantum that was 22.2 per cent more than the 70,728 MVA added in FY24. The FY25 performance on the substation front was in pleasant contrast Read more

Substation capacity addition grows 18 per cent in Apr-Nov FY25

Healthy substation capacity addition was witnessed in the first eight months (April to November) of FY25. According to latest statistics released by Central Electricity Authority (CEA), the total transformation (substation) capacity addition during the April-November period Read more

L&T

Substation capacity addition meets only 43 per cent of target

Substation capacity addition in the first five months (April to August) of current fiscal year FY25 has met only 43 per cent of the target. As against 42,230 MVA of substation capacity planned for addition in the April-August period Read more

Record substation capacity addition likely in FY25

    India is likely to witness record transformation capacity addition in FY25, going by official statistics. Latest reports by Central Electricity Authority (CEA) suggest that in the current fiscal year FY25 (April 1, 2024 to March 31, Read more

Linxon PGCIL Saharsa SS LR | T&D India

Substation capacity addition falls 7 per cent in FY24

    Addition of substation (transformation) capacity in FY24 was 6.8 per cent lower than in FY23, according to a special study by T&D India. The study, based on time series data released by Central Electricity Authority, suggests that substation capacity Read more

Substation capacity addition falls 19 per cent in 9MFY24

    The total substation (transformation) capacity added in the first nine months of FY24 was 19 per cent lower than in the same period of FY23. According to latest statistics released by Central Electricity Authority (CEA), India Read more

Linxon SS | T&D India

Substation capacity addition falters at 765kV level

    Substation capacity addition during the first eight months (April to November) of FY24 fell substantially short of the target, especially considering the 765kV voltage class. According to latest statistics released by the Central Electricity Authority (CEA), Read more

Substation capacity addition meets just half of target

  India’s substation capacity addition in the first half (April to September) of FY24 barely met 50 per cent of the planned addition. According to latest official statistics, India saw the addition of 22,126 MVA of substation (transformation) capacity in Read more

Substation capacity addition meets less than half of target

  The quantum of new transformation capacity added in the first four months of FY24 was less than half of the planned addition. According to latest statistics released by Central Electricity Authority (CEA), a total of 14,016 Read more