Linxon PGCIL Saharsa SS LR | T&D India

Substation capacity addition falls 7 per cent in FY24

    Addition of substation (transformation) capacity in FY24 was 6.8 per cent lower than in FY23, according to a special study by T&D India. The study, based on time series data released by Central Electricity Authority, suggests that substation capacity Read more

Substation capacity addition falls 19 per cent in 9MFY24

    The total substation (transformation) capacity added in the first nine months of FY24 was 19 per cent lower than in the same period of FY23. According to latest statistics released by Central Electricity Authority (CEA), India Read more

Linxon SS | T&D India

Substation capacity addition falters at 765kV level

    Substation capacity addition during the first eight months (April to November) of FY24 fell substantially short of the target, especially considering the 765kV voltage class. According to latest statistics released by the Central Electricity Authority (CEA), Read more

Substation capacity addition meets just half of target

  India’s substation capacity addition in the first half (April to September) of FY24 barely met 50 per cent of the planned addition. According to latest official statistics, India saw the addition of 22,126 MVA of substation (transformation) capacity in Read more

Substation capacity addition meets less than half of target

  The quantum of new transformation capacity added in the first four months of FY24 was less than half of the planned addition. According to latest statistics released by Central Electricity Authority (CEA), a total of 14,016 Read more

Linxon India | T&D India

Substation capacity addition almost meets target in FY23

  The total substation capacity addition in FY23 stood at 75,902 MVA, meeting 96.1 percent of the target, which incidentally, was revised downwards on two occasions. According to an analysis by T&D India based on official statistics released by Central Read more

MPPTCL

220kV substation capacity addition on track in FY23

  The pace of the addition of 220kV transformation (substation) capacity appears to be on track in FY23, though there has been a substantial shortfall in higher voltage levels like 400kV and 765kV. According to official statistics recently released by Read more