The option of using HVDC-based power transmission technology for the mega transmission scheme to evacuate 5 GW of renewable energy from Leh in UT of Ladakh is now ruled out.
In the latest meeting held by National Committee on Transmission (NCT) recently, it was agreed that HVDC technology would be infeasible for various technical reasons.
Moreover, the only other alternative – that of using EHVAC – would be pursued only after Power Grid Corporation of India Ltd (PGCIL) completes detailed studies on the matter.
As reported by tndindia.com on August 6, 2025, R.K. Tyagi, CMD, PGCIL, had explained that HVDC technology was proving infeasible as only one HVDC OEM supplier expressed interest in the project that was supposed to use VSC-based HVDC technology. Even here, apprehensions were voiced on whether HVDC technology would work in hostile geographic and climatic conditions.
During the recent NCT meeting, PGCIL submitted that it had carried out front end engineering design (FEED) studies at both network level and equipment level. A primary conclusion derived was that the complex geography of the Pang pooling station that is at an altitude of 4,700m and subject to sub-zero temperatures that could even reach -35°C, no VSC-based HVDC technology would be available or feasible.
It has now been decided that EHVAC transmission systems would be exclusively used, albeit with more studies. Even here, as reported in tndindia.com’s story referred to earlier, there were concerns about the use of synchronous condensers (SynCons) that will be critical in achieving much needed dynamic reactive compensation, as the transmission system would be dealing with RE power.
PGCIL, as decided in the NCT meeting, will carry out studies regarding the use of EHVAC with respect to equipment needed and firmness of design. In parallel, the Union ministry of new & renewable energy (MNRE) will engage with RE developers to get their feedback on the working of inverters in areas of high altitude and low temperature, as well as on the use of SynCons. Central Transmission Utility of India Ltd (CTUIL), in consultation with CEA, will review the transmission scheme to enhance system stability, especially ensuring supply of green energy to Himachal Pradesh.
NCT will be revisiting the project in a subsequent meeting after due feedback from PGCIL, MNRE and CTUIL, it is learnt.
The ISTS scheme is termed as “Transmission system for evacuation of 5 GW RE power from Renewable Energy Parks in Leh.” The project is proposed for implementation by PGCIL under the regulated tariff mechanism (RTM) route.
In the original design, where HVDC technology was being considered, the project involved putting up a ±350kV VSC-based system between Pang Pooling Station (in UT of Ladakh) and Kaithal Pooling Station (in Haryana). The two pooling stations would also be developed as part of the project.
There was also an AC system strengthening in Ladakh to provide RE power to UT of Ladakh and UT of J&K through the 220kV Pang-Leh single-circuit line. Besides, an EHVAC system for dispersal of power to load centres towards Modipuram (Meerut district, Uttar Pradesh) at 765kV and towards Bahadurgarh (Jhajjar district, Haryana) at 400kV, was also part of the overall project.
Also read: HVDC chosen over BESS for Rajasthan RE evacuation scheme
Featured photograph is for representation only