Current fiscal year FY26 is likely to close with a significant deficit in addition of 765kV transmission lines.
The private sector is likely to commission a higher quantum of power transmission infrastructure in FY26 as compared with the actual achievement in FY25, a study by tndindia.com suggests.
It is now confirmed that the mega Ladakh renewable energy (RE) evacuation scheme will be implemented using EHVAC technology, instead of the earlier planned combination of HVDC and EHVAC. However, the final approval by National Committee on Transmission (NCT) will be accorded only after Ministry of New & Renewable Energy (MNRE) provides its technical inputs.
In a rare occurrence, no new interstate transmission system (ISTS) scheme under the tariff-based competitive bidding (TBCB) mechanism was cleared at the latest National Committee on Transmission (NCT).
The interstate transmission system (ISTS) network has witnessed healthy addition of transformation (substation) capacity addition during the current fiscal year.
The pace of transmission line addition picked up in October 2025, according to latest official statistics, but the cumulative performance in FY26 is still far below the target.
An estimated 15 interstate transmission system (ISTS) schemes that were awarded under the tariff-based competitive bidding route (TBCB) are likely to be commissioned during the third quarter (Q3: October to December) of FY26.
During the period January 1, 2025 to June 30, 2025, 22 cases of EHV transmission line failure due to towers were reported by 11 utilities to the Standing Committee of Experts constituted by the Central Electricity Authority (CEA).
India’s substation capacity addition during the first half (H1: April to September) of FY26 was up 74 per cent, year-on-year, but still met only two-thirds of the planned addition.
India’s very first project for deploying of synchronous condenser (SynCon) units for implementation under the TBCB route was recently approved by NCT.