Major shortfall foreseen in 765kV transmission line addition in FY26

Current fiscal year FY26 is likely to close with a significant deficit in addition of 765kV transmission lines.

Read more

Big increase foreseen in transmission infrastructure build-up by private sector

The private sector is likely to commission a higher quantum of power transmission infrastructure in FY26 as compared with the actual achievement in FY25, a study by tndindia.com suggests.

Read more

Ladakh RE evacuation scheme: EHVAC found feasible, NCT’s approval awaited

It is now confirmed that the mega Ladakh renewable energy (RE) evacuation scheme will be implemented using EHVAC technology, instead of the earlier planned combination of HVDC and EHVAC. However, the final approval by National Committee on Transmission (NCT) will be accorded only after Ministry of New & Renewable Energy (MNRE) provides its technical inputs.

Read more

No new interstate transmission scheme under TBCB approved at latest NCT meet

In a rare occurrence, no new interstate transmission system (ISTS) scheme under the tariff-based competitive bidding (TBCB) mechanism was cleared at the latest National Committee on Transmission (NCT).

Read more

Interstate transmission network sees healthy addition of transformation capacity

The interstate transmission system (ISTS) network has witnessed healthy addition of transformation (substation) capacity addition during the current fiscal year.

Read more

Transmission line addition picks up in October 2025 but still short of target

The pace of transmission line addition picked up in October 2025, according to latest official statistics, but the cumulative performance in FY26 is still far below the target.

Read more

Full commissioning of 15 ISTS-TBCB schemes expected in Q3FY26

An estimated 15 interstate transmission system (ISTS) schemes that were awarded under the tariff-based competitive bidding route (TBCB) are likely to be commissioned during the third quarter (Q3: October to December) of FY26.

Read more

EHV transmission line tower failure: 22 cases reported in January-June 2025

During the period January 1, 2025 to June 30, 2025, 22 cases of EHV transmission line failure due to towers were reported by 11 utilities to the Standing Committee of Experts constituted by the Central Electricity Authority (CEA).

Read more

Substation capacity addition up 74 per cent, but short of target

India’s substation capacity addition during the first half (H1: April to September) of FY26 was up 74 per cent, year-on-year, but still met only two-thirds of the planned addition.

Read more

India’s first synchronous condenser (SynCon) project under TBCB, approved

India’s very first project for deploying of synchronous condenser (SynCon) units for implementation under the TBCB route was recently approved by NCT.

Read more